Software Process MCQs. Multiple Choice Questions related to Software Process and different stages involved in the Software Process.

The longer a fault exists in software ?

A. the more tedious its removal becomes
B. the more costly it is to detect and correct
C. the less likely it is to be properly corrected
D. All of the mentioned

View Answer

D. All of the mentioned

How is WINWIN Spiral Model different from Spiral Model ?

A. It defines tasks required to define resources, timelines, and other project related information
B. It defines a set of negotiation activities at the beginning of each pass around the spiral
C. It defines tasks required to assess both technical and management risks
D. It defines tasks required to construct, test, install, and provide user support

View Answer

B. It defines a set of negotiation activities at the beginning of each pass around the spiral

How is Incremental Model different from Spiral Model ?

A. Progress can be measured for Incremental Model
B. Changing requirements can be accommodated in Incremental Model
C. Users can see the system early in Incremental Model
D. All of the mentioned

View Answer

A. Progress can be measured for Incremental Model